Add up what one job really cost — materials, loaded labor, subs, fees and its share of overhead and the truck — and see what it made, what it needed to break even, and what to bid next time.
1Job cost (management view)
Example job: $1,100 of materials and 4 labor hours, costed with the example shop’s $66.07 labor and $46.61 overhead + truck per billable hour. Change any number.
Net job profitExample job
$749.2831.22% net margin
Net job profit $749.28, 31.22% of the price; break-even price $1,650.72.
Job cost build-upDrawn to scale: every dollar the same height
1Materialsat what you paid$1,100.00
2Labor4 h × $66.07$264.28
3Subs and feespermit $75, disposal $25$100.00
4Overhead + truck4 h × $46.61$186.44
5Net profit31.22% of the price$749.28
Direct cost
$1,464.28materials, labor, subs, fees
Overhead + truck
$186.444 h × $46.61
Total job cost
$1,650.72= the break-even price
Gross margin
38.99%before overhead
Net margin
31.22%after overhead
Markup on cost
45.39%on total job cost
Break-even
$1,650.72price = total cost
Gross profit
$935.7238.99% of the price
At 10% net
$1,834.13price to bid
$2,400.00 − $1,650.72= $749.2831.22% of the price
Already showing the example.
Materials include any sales tax you paid when you bought them; nothing is added to the customer’s bill.
This is a management view of one job, not how its costs are classified for taxes. Ask your accountant how to report them.
What moves this job
One more labor hour costs $112.68 (labor + overhead) and leaves $636.60 net, 26.53%.
The job breaks even at 10.65 labor hours — 6.65 h more than it took.
How the math works
A job pays for its own materials, labor and fees first; then it has to carry its share of the shop’s overhead and truck for the hours it used. What is left is the job’s net profit.
Labor costlabor hours × loaded labor cost per billable hourExample: 4 h × $66.07 = $264.28. Not the wage: only billable hours can be charged to jobs, so unbillable time rides on them.
Direct costmaterials + labor + subs + permits + disposal + otherExample: $1,464.28. A management (job-cost) view, not the Schedule C classification.
Gross profitprice − direct costExample: $935.72, 38.99% of the price.
Overhead + trucklabor hours × (overhead + truck) per billable hourExample: 4 h × $46.61 = $186.44.
Break-even pricedirect cost + overhead + truck = $1,650.72The total job cost: where total cost equals revenue (SBA’s break-even definition).
Net job profitprice − total job cost = $749.28Net margin 31.22%; markup on total cost 45.39%.
Price for a target margintotal job cost ÷ (1 − target net margin)Example at 10%: $1,650.72 ÷ 0.90 = $1,834.13.
Sales tax collectedtaxable amount × your rateShown as a pass-through line, outside the job’s price: collecting it changes no profit or margin here. How it is treated for income tax depends on how your state imposes it — ask your accountant.
Where the example numbers come from
Loaded labor cost
$66.07 per billable hourLabor rate calculator, example shop: BLS median plumber wage, IRS and DOL payroll taxes, BLS benefits, 65% billable (site arithmetic)
Overhead + truck
$32.87 + $13.74 = $46.61 per billable hourLabor rate calculator: $120,000 overhead for 3 techs (an editorial example) and the AAA 2026 ½-ton pickup
Permit
$75Example only. Angi lists plumbing permit fees of $75–$100 (consumer cost guide); permits are set by each city or county
Disposal
$25Editorial example for a small item; no source gives a typical trade dump fee
Materials, hours, price
$1,100 · 4 h · $2,400Editorial example: no claim about market prices
Sales tax rate
NoneState and local rates vary; enter your own combined rate
Before you use the number
Sales tax depends on your state, the contract type and the item. In at least four of the six states read, a contractor installing materials into real property generally pays tax when buying them — but the answer flips for fixtures in California, separated or nonresidential contracts in Texas, repair services in New York and all custom construction in Washington. Ask your state revenue department or a tax professional.
Collected sales tax is not your money and is never counted as revenue or profit here. How it is treated for income tax depends on how your state imposes it — ask your accountant.
Labor here is cost per billable hour, not the wage. With the example shop, the wage ($30.67) understates labor cost by more than half: it leaves out taxes, insurance, benefits, paid time off and unbillable time.
Overhead per hour is an average. A job that ties up the truck or the office far more than its labor hours suggest (permits, inspections, long drives) costs more than the average.
A positive gross margin can still be a loss once overhead is counted: the same job at $1,600 has an 8.48% gross margin and a net loss of $50.72.
Not for tax filing or accounting records. Direct cost here is a management view; IRS Publication 334 says labor is usually part of cost of goods sold only in manufacturing or mining.
Sources
Opened and checked October 4, 2026 (the Florida rule on October 24, 2026). The worked example is the site’s own arithmetic.
Markup is on cost, margin is on price. Formulas, a conversion table, the classic mistakes and a water heater swap with labor, parts, tax and card fees.